Timothy Lutheran Church

Despite being constructed during the winter, this tilt-up church project beat the original schedule by one month and was delivered under budget. The wall panels for the multi-purpose area were stack cast, since the area of the wall panels was larger than the building’s footprint. The exterior finishes consist of a direct applied finish system, metal panel cladding, and cast-in brick.

Client
Meyer Brothers Building Company
Location
Blue Springs, MO