Rebecca Trunk Wastewater Main

  •  
  • Role: Microtunnel Designer & Construction Inspection/Administration
  • Client: Cole Engineering
  • Construction Cost: $43 Million
  • Technology: Drill and Blast
  • Geology: Rock
  • Diameter: 1,200mm (48 in) & 1,350mm (54 in)
  • Length: 12,476 m & 1,575 m
  • Depth: 14 m (46 ft)

Project Elements:

  • Fourteen (14) microtunneling drives
  • Twelve (12) composite curved drives
  • Long microtunneling drives from 180m to 626m
  • Concrete caisson shafts
  • Shallow crossing of environmentally sensitive creek
Client
Cole Engineering
Location
Oakville, ON
Morrison Bridge Rehabilitation

Morrison Bridge Rehabilitation

In 1874, the Morrison brothers built a cast-and-wrought-iron bowstring arch bridge…
Benchwood Station Transportation Improvements

Benchwood Station Transportation Improvements

LJB helped shape the future of the Benchwood Station District, Butler…
Olentangy Augmentation Relief Sewer (OARS) Construction Management

Olentangy Augmentation Relief Sewer (OARS) Construction Management

Role: Construction Management, Technical Support Client: City of Columbus Construction Cost: $375…