Atlanta Airport Plane Train Turnback Tunnel

  •  
  • Role: Owner’s Engineer for tunnel and Access Shaft; Progressive Design Build
  • Client: Ricondo
  • Construction Cost: $140 Million
  • Technology: CSEM, Drill and Blast
  • Geology:  Soil/Rock
  • Dimensions: 22 ft (6.7 m); Tunnel bifurcation up to 48 ft (14.5 m) span
  • Length: 1780 ft (237 m)
  • Depth: 36-55 ft (11-17 m)

Project Elements:

  • (x1) Access Shaft – 36 ft ID x 56 ft deep
  • Tunnel connecting main terminal and intercontinental hotel
  • Geotecnical data review
  • 30% design drawings
  • Preparation for bidding
  • Review and approval of Contractor’s design
Client
Ricondo
Location
Atlanta, GA
Montreal Airport Station, Transit Terminal for REM

Montreal Airport Station, Transit Terminal for REM

Role: Tunnel, Shaft and Station cavern Design – Precast Concrete Liners, Connections…
Rebecca Trunk Wastewater Main

Rebecca Trunk Wastewater Main

Role: Microtunnel Designer & Construction Inspection/Administration Client: Cole Engineering Construction Cost: $43…
Crenshaw/LAX Transit Corridor

Crenshaw/LAX Transit Corridor

Role: SOE Design of Stations; Design Build for Contractor Client: Walsh-Shea Constructors…