- Role: Tunnel, Shaft and Station cavern Design – Precast Concrete Liners, Connections and Complex Fault Crossings
- Client: Aeroports de Montreal
- Construction Cost: $600 Million
- Technology: Drill and Blast
- Geology: Rock
- Length: 815 ft (250 m)
- Diameter: 31 ft (9.6 m) with 79 ft (24 m) span cavern
- Depth: 86-142 ft (26-43 m)
Project Elements:
-
- Design of cavern under terminal building
- Access tunnel design
- Track bifurcation caverns design
- Cost estimating
- Risk management and risk workshops
- Quantitative risk analysis of budget and schedule